Title: CATCH BASIN CONNECTOR PIPE SCREEN INSTALLATION PROJECT
Attachments: 1. 051920 PW Catch Basin Connector Pipe Screen Installation Project Agenda Report, 2. 051920 PW Catch Basin Connector Pipe Screen Installation Project Budget Data Sheet, 3. 051920 PW Catch Basin Connector Pipe Screen Installation Project Location Map, 4. 051920 PW Catch Basin Connector Pipe Screen Installation Project Consultant Agreement

Title

CATCH BASIN CONNECTOR PIPE SCREEN INSTALLATION PROJECT

Recommendation

Recommendation:

 

1.                     Approve and authorize Public Works Director to enter into $93,130 agreement with G2 Construction, Inc. of Garden Grove for installation of full capture trash inserts in existing catch basins under Orange County Transportation Authority Environmental Cleanup, Tier 1 Grant Program, in a form approved by the City Attorney.

 

2.                     Approve $30,837 budget transfer and appropriation from Sanitation Fund Balance to Project 52694 Catch Basin Connector Pipe Screen Installation Project.

 

3.                     Authorize Director of Public Works, or approved designee, to approve any future change orders within approved project budget.