File #: 21-901   
Type: Consent Calendar Status: Agenda Ready
In control: City Council - Successor Agency - Housing Authority
On agenda: 12/7/2021 Final action:
Title: GILBERT STREET / IRIS COURT WATER MAIN REPLACEMENT
Attachments: 1. 120721 PW Gilbert / Iris Water Main Replacement Agenda Report, 2. 120721 PW Gilbert / Iris Water Main Replacement Budget Data Sheet, 3. 120721 PW Gilbert / Iris Water Main Replacement Bid Schedule, 4. 120721 PW Gilbert / Iris Water Main Replacement Project Location, 5. 120721 PW Gilbert / Iris Water Main Replacement Standard Agreement

Title

GILBERT STREET / IRIS COURT WATER MAIN REPLACEMENT

Recommendation

Recommendation:

 

1.                     Approve Gilbert Street / Iris Court Water Main Replacement Project plans and specifications.

 

2.                     Approve $634,000 Water Fund transfer from Project 53250 Water Main System Replacement to Project 53033 Gilbert Street / Iris Court Water Main Replacement Project (Fund 44).

 

3.                     Award $496,363 construction contract for the Gilbert Street / Iris Court Water Main Replacement Project to Gutierrez Pipeline Inc. and authorize City Manager, or designee, to execute the contract, in a form approved by the City Attorney.

 

4.                     Authorize Public Works Director, or designee, to approve any future change orders for construction and professional engineering construction support services within the approved project budget.