File #: 21-1058   
Type: Consent Calendar Status: Agenda Ready
In control: City Council - Successor Agency - Housing Authority
On agenda: 10/19/2021 Final action:
Title: STORM DRAIN LINING FISCAL YEAR 2020-21 PROJECT
Attachments: 1. 101921 PW Storm Drain Lining FY 20-21 Agenda Report, 2. 101921 PW Storm Drain Lining FY 20-21 Budget Data Sheet, 3. 101921 PW Storm Drain Lining FY 20-21 Bid Schedule, 4. 101921 PW Storm Drain Lining FY 20-21 Location Map, 5. 101921 PW Storm Drain Lining FY 20-21 Standard CIP Agreement

Title

STORM DRAIN LINING FISCAL YEAR 2020-21 PROJECT

Recommendation

Recommendation:

 

1.                     Approve Storm Drain Lining FY 2020-21 Project plans and specifications.

 

2.                     Approve $120,000 transfer from Project 52591 Annual Storm Drain Repair to Project 52719 Storm Drain Lining FY 2020-21 Project (Fund 74).

 

3.                     Award $92,137 construction contract for Storm Drain Lining FY 2020-21 to Nor-Cal Pipeline Services, Inc. and authorize the City Manager, or designee, to execute the contract, in a form approved by the City Attorney.

 

4.                     Authorize Public Works Director to approve any future change orders for construction and professional engineering construction support services within the approved project budget.