$1,579,250 CONTRACT WITH WILLIAMS PIPELINE CONTRACTORS, INC. FOR COURTNEY-ASH AREA WATER MAIN REPLACEMENT
Recommendation
Proposed Motion:
1. Approve Courtney-Ash Area Water Main Replacement Project 53049 plans and specifications.
2. Approve $1,830,000 Water Fund budget transfer and appropriation from Capital Improvement Program (CIP) Project 53250 Water Main System Replacement to CIP Project 53049 Courtney-Ash Area Water Main Replacement within the Water Fund (Fund 44).
3. Award $1,579,250 construction contract for Courtney-Ash Area Water Main Replacement Project to Williams Pipeline Contractors, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve change orders for construction and professional engineering construction support services within the approved project budget.