Title: $1,579,250 CONTRACT WITH WILLIAMS PIPELINE CONTRACTORS, INC. FOR COURTNEY-ASH AREA WATER MAIN REPLACEMENT
Attachments: 1. 081925 PW Courtney-Ash Area Water Main Replacement Agenda Report, 2. 081925 PW Courtney-Ash Area Water Main Replacement Budget Data Sheet, 3. 081925 PW Courtney-Ash Area Water Main Replacement Bid Schedule, 4. 081925 PW Courtney-Ash Area Water Main Replacement Project Location Map, 5. 081925 PW Courtney-Ash Area Water Main Replacement Draft CIP Agreement

Title

$1,579,250 CONTRACT WITH WILLIAMS PIPELINE CONTRACTORS, INC. FOR COURTNEY-ASH AREA WATER MAIN REPLACEMENT

Recommendation

Proposed Motion:

 

1.                     Approve Courtney-Ash Area Water Main Replacement Project 53049 plans and specifications.

 

2.                     Approve $1,830,000 Water Fund budget transfer and appropriation from Capital Improvement Program (CIP) Project 53250 Water Main System Replacement to CIP Project 53049 Courtney-Ash Area Water Main Replacement within the Water Fund (Fund 44).

 

3.                     Award $1,579,250 construction contract for Courtney-Ash Area Water Main Replacement Project to Williams Pipeline Contractors, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.

 

4.                     Authorize Public Works Director, or designee, to approve change orders for construction and professional engineering construction support services within the approved project budget.