Title
$2,389,800 CONTRACT WITH WILLIAMS PIPELINE CONTRACTORS, INC. FOR THE ASH-WOODS AREA INFRASTRUCTURE IMPROVEMENTS PROJECT
Recommendation
Proposed Motion:
1. Approve the Ash-Woods Area Infrastructure Improvements Project plans and specifications.
2. Approve the following budget transfers and appropriations in Project 53061 Ash-Woods Area Infrastructure Improvements Project:
• $2,180,500 Water Fund (Fund 44) transfer and appropriation from Project 53250 Water Main System Replacement to Project 53061 Ash-Woods Area Infrastructure Improvements Project within the Water Fund (Fund 44)
• $659,500 Sewer Enterprise Funds (Fund 47) transfer and appropriation from Project 51419 Annual Sewer Replacement Program to Project 53061 Ash-Woods Area Infrastructure Improvements Project within the Sewer Enterprise Fund (Fund 47).
3. Award $2,389,800 construction contract for the Ash-Woods Area Infrastructure Improvements Project to Williams Pipeline Contractors, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve change orders for construction and professional engineering construction support services within the approved project budget.