Title
$1,138,075 CONTRACT WITH R.J. NOBLE COMPANY FOR THE HARBOR BOULEVARD REHABILITATION PROJECT
Recommendation
Proposed Motion:
1. Approve Project 44083 Harbor Boulevard Rehabilitation Project plans and specifications.
2. Approve the following budget transfers and appropriations in Project 44083 Harbor Boulevard Rehabilitation Project:
• $1,370,000 Measure M2 Fund (Fund 25) budget transfer and appropriation from Project 44400 Street Reconstruction, Rehabilitation and Repair to Project 44083 Harbor Boulevard Rehabilitation within the Capital Projects Fund (Fund 74).
• $50,000 Sewer Enterprise Fund (Fund 47) budget transfer and appropriation from Project 51419 Annual Sewer Replacement Program to Project 44083 Harbor Boulevard Rehabilitation within the Sewer Enterprise Fund (Fund 47).
3. Approve bid alternate work and include in the project scope of work.
4. Award a $1,138,075 construction contract for 44083 Harbor Boulevard Rehabilitation Project to R.J. Noble Company and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.
5. Authorize Public Works Director, or designee, to approve change orders for construction and professional engineering construction support services within the approved project budget.
6. Waive Fullerton Municipal Code Section 15.90 Noise Standards and Regulation to allow project street pavement rehabilitation at night adjacent to commercial and residential properties.