File #: 25-0205   
Type: Consent Calendar Status: Agenda Ready
In control: City Council - Successor Agency - Housing Authority
On agenda: 4/15/2025 Final action:
Title: $649,044 CONTRACT WITH COPP CONTRACTING, INC. FOR HOLLYDALE AREA STREET REHABILITATION
Attachments: 1. 041525 PW Hollydale Area Street Rehabilitation Agenda Report, 2. 041525 PW Hollydale Area Street Rehabilitation Budget Data, 3. 041525 PW Hollydale Area Street Rehabilitation Bid Schedule, 4. 041525 PW Hollydale Area Street Rehabilitation Project Location Map, 5. 041525 PW Hollydale Area Street Rehabilitation Draft CIP Agreement

Title

$649,044 CONTRACT WITH COPP CONTRACTING, INC. FOR HOLLYDALE AREA STREET REHABILITATION

Recommendation

Proposed Motion:

 

1.                     Approve Hollydale Area Street Rehabilitation Project plans and specifications.

 

2.                     Approve the following budget transfers and appropriations in CIP Project 44077 Hollydale Area Street Rehabilitation:

 

                     $780,000 Infrastructure Funds (Fund 74) transfer and appropriation from CIP Project 44400 Street Reconstruction and Rehabilitation Program to CIP Project 44077 Hollydale Area Street Rehabilitation within the Capital Projects Fund (Fund 74)

 

                     $40,000 Sewer Enterprise Fund (Fund 47) transfer and appropriation from CIP Project 51419 Annual Sewer Replacement Program to CIP Project 44077 Hollydale Area Street Rehabilitation within the Sewer Enterprise Fund (Fund 47).

 

3.                     Award $649,044 construction contract for Hollydale Area Street Rehabilitation Project to Copp Contracting, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.

 

4.                     Authorize Public Works Director, or designee, to approve change orders for construction and professional engineering construction support services within the approved project budget.