File #: 24-0240   
Type: Consent Calendar Status: Agenda Ready
In control: City Council - Successor Agency - Housing Authority
On agenda: 5/7/2024 Final action:
Title: CONTRACT WITH ALL CITIES ENGINEERING, INC. FOR EUCLID AND ROSECRANS WATER MAIN REHABILITATION PROJECT
Attachments: 1. 050724 PW Euclid and Rosecrans Water Main Rehabilitation Agenda Report, 2. 050724 PW Euclid and Rosecrans Water Main Rehabilitation Budget Data, 3. 050724 PW Euclid and Rosecrans Water Main Rehabilitation Bid Schedule, 4. 050724 PW Euclid and Rosecrans Water Main Rehabilitation Location Map, 5. 050724 PW Euclid and Rosecrans Water Main Rehabilitation Draft CIP Agreement

Title

CONTRACT WITH ALL CITIES ENGINEERING, INC. FOR EUCLID AND ROSECRANS WATER MAIN REHABILITATION PROJECT

Recommendation

Proposed Motion:

 

1.                     Approve plans and specifications for the Euclid and Rosecrans Water Main Rehabilitation Project.

 

2.                     Approve the following budget transfers to and appropriations in CIP Project 53051 Euclid and Rosecrans Water Main Rehabilitation:

 

                     Transfer and appropriate $2,780,000 Water Fund (Fund 44) from CIP Project 53250 Water Main System Replacement to CIP Project 53051 Euclid and Rosecrans Water Main Rehabilitation within the Water Fund (Fund 44)

 

                     Transfer and appropriate $320,000 Sewer Enterprise Fund (Fund 47) from CIP Project 51419 Annual Sewer Replacement Program to CIP Project 53051 Euclid and Rosecrans Water Main Rehabilitation within the Sewer Enterprise Fund (Fund 47).

 

3.                     Award $2,576,550 construction contract for Euclid and Rosecrans Water Main Rehabilitation Project to All Cities Engineering, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.

 

4.                     Authorize Public Works Director, or designee, to approve any future change orders for construction and professional engineering construction support services within the approved project budget.