Title
$1,615,495 CONTRACT WITH DOMINGUEZ GENERAL ENGINEERING, INC FOR YUCCA AREA WATER MAIN REPLACEMENT
Recommendation
Proposed Motion:
1. Approve Yucca Area Water Main Replacement Project 53057 plans and specifications.
2. Approve $1,869,000 Water Fund (Fund 44) budget transfer and appropriation from Capital Improvement Program (CIP) Project 53250 Water Main System Replacement to CIP Project 53057 Yucca Area Water Main Replacement within the Water Fund (Fund 44).
3. Award $1,615,495 construction contract for Yucca Area Water Main Replacement Project to Dominguez General Engineering, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve any future change orders for construction and professional engineering support services within the approved project budget.