$280,000 CONTRACT WITH HARDY AND HARPER, INC. FOR AMERIGE AVENUE REHABILITATION PROJECT
Recommendation
Proposed Motion:
1. Approve Amerige Avenue Rehabilitation Project plans and specifications.
2. Approve $375,000 General Funds (Fund 10) budget transfer and appropriation from Project 44400 Arterial Street Program to Project 44082 Amerige Avenue Rehabilitation within the Capital Projects Fund (Fund 74).
3. Award $280,000 construction contract for Amerige Avenue Rehabilitation Project to Hardy and Harper, Inc. and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve construction and professional engineering construction support services change orders within the approved project budget.